Costs of Setting Up a New Business

Operations

March 26, 2026

$45M total one-time startup investment for 1 MW BTM hydro GPU facility across 14 cost items in 10 categories

Icon
$45M TOTAL CAPEX
$45,000,000
Total Startup Investment (incl. contingency)
14
Cost Items
10
Categories
~13%
Contingency
$0
Electricity
CAPEX Distribution by Segment
59%
Compute Hardware
$26.5M
25%
Infrastructure
$11.16M
13%
Contingency
~$5.22M
<1%
Soft Costs
~$120K
Itemized Startup Cost Breakdown
CategoryCost ItemShareAmount
Compute4x GR200 NVL72 (288 GPU + 144 Grace CPU)
$26,500,000
NetworkingInfiniBand NDR800, fat-tree topology
$4,800,000
StorageAll-NVMe, ~1.5 PB usable
$2,100,000
CoolingDirect Liquid Cooling (DLC) system
$1,600,000
CivilPrefab modular containers, seismic-rated
$1,600,000
PowerUPS 200 kW + distribution (no BESS)
$1,060,000
IntegrationSystem integration, testing, commissioning
$1,000,000
ConnectivityFiber build + Starlink backup
$500,000
SoftwareNVIDIA stack, orchestration platform
$500,000
ProfessionalLegal counsel (JV), accounting setup [A]
$50,000
RecruitmentCTO, Head of Energy, Sales [A]
$30,000
Pre-launchTravel, site visits, due diligence [A]
$25,000
AdvisoryAdvisory board agreements [A]
$10,000
LegalGeorgia LLC (Virtual Zone), trademark [A]
$5,000
TOTAL (incl. ~$5.2M contingency)$45,000,000
Key Notes
Electricity = $0 — behind-the-meter JV structure, not a cost line item
Contingency ~$5.22M (~13%) built into total, not itemized separately
Items marked [A] = Assumption — REL estimates pending confirmation
All amounts USD, gross before financing adjustments
No recurring OPEX included — startup costs only (pre-commercial)
1 MW facility: 4x GR200 NVL72 racks, 288 GPU, PUE < 1.10